Ogilvy v Hope Davies | |
---|---|
Court | High Court |
Citation(s) | [1976] 1 All ER 683 |
Keywords | |
Estoppel |
Ogilvy v Hope Davies [1976] 1 All ER 683 is an English contract law case concerning promissory estoppel.
Contents |
Ogilvy was selling the Creech Hill Farmhouse, Cranborne to Hope Davies. An abstract of title to the house needed to be sent to Hope Davies' solicitors, but Ogilvy, as a trustee failed to include the deed of appointment as trustee until later on. Hope Davies' solicitors delayed making requisitions and completion till the deed was sent, and this put Ogilvy at a loss. Ogilvy sued for losses resulting from the delayed completion.
Graham J held that Hope Davies' solicitors should have raised requisitions on the defective abstract of title, because it was defective only in ways which were relatively unimportant and likely to be corrected. The late delivery of the deed of appointment, together with a letter sent by the vendors asking that all the requisitions be raised at the same time, amounted to a waiver by Ogilvy of the time limits on requisitions, and it would be inequitable to allow them to claim for losses occasioned by the delay.
“ | It is it seems to me a case which might well not have come before this court if the instructing solicitors on both sides had not, as the correspondence shows, become irritated with each other shortly after the end of the summer term in 1973.
As it is, the small amount at stake, £503.60, is bound to be swallowed up in fighting the case to no one's advantage. In the absence of a settlement, however, which would clearly have been sensible, I must decide the matter on what I conceive to be the proper legal basis... Legally, I consider the position is governed by the principles of waiver or promissory estoppel, however it may be classified, which are set out for example, in the judgment of Lord Denning M.R. in W.J. Alan & Co. Ltd. v. El Nasr Export and Import Co.[1] There, after referring to Panoutsos v. Raymond Hadley Corporation of New York[2] and Enrico Furst & Co. v. W.E. Fisher Ltd.,[3] he says:[4]
So here it would, in my judgment, in all the circumstances, be inequitable, to allow the plaintiffs to insist on the strict rights to which they would have been entitled if they had not led the defendant to believe that they were not insisting on them. The time was in fact getting very short when they wrote the letter of August 15, 1973, and this, coupled with the failure to deliver the deed of appointment until August 20, entitled the defendant to assume that completion by August 30, 1973, would, not in fact be possible. Any question of withdrawal of the waiver was impossible before August 30 because the time was impossible before August 30 because the time was far too short. The plaintiffs' therefore fail and the defendant is entitled to judgment. |
” |
|